Results of PGTF - Project INT/10/K04

Submitter: Biomass Institute of the Ministry of Agriculture (BIOMA), based in Chengdu, China.
Subcontractor: Same as above.
Priority area: Energy.
Participating/beneficiary countries: 3 countries (Bangladesh, China and the Philippines).
PGTF input: US$ 29,000.
Other inputs: US$ 51,000.
Number: INT/10/K04.
Duration: 2018-2019.
Approval: 33rd Annual Ministerial Meeting of the Group of 77 (New York, 25 September 2009).
Completion: Final report submitted on 6 August 2019.
Impact: Demonstrated the use of low-cost reinforced fiberglass biogas digesters to treat animal waste and generate clean and efficient energy in selected rural areas in Bangladesh and the Philippines, and provided hands-on training to local technicians and officials in agriculture and environment sectors in the Philippines and Bangladesh in the installation and operation of biogas digesters.

Contact:   Contact person: Long Yan
Address: No. 13, Section 4, South Renmin Road, Chengdu, China
Telephone: 0086-15108377811
Fax: 0086-28-85230677
Email: cclonglong @ yahoo.com.cn


Final Report:

    • INT-10-K04-FinalReport.pdf  *  [Language: English; Size: 5128KB]


    • _____________________
      * Note: The reports posted have been prepared by the submitting institutions and their content is the sole responsibility of their authors. Please forward any inquiries or requests for further information to the contact person provided and kindly send a copy to the Office of the Chairman of the Group of 77 for our records.